HO PC-90 Piggy-Packer Update
A few of you have asked about the schedule of our HO scale PC-90 Piggy-Packer so here's the latest.
Pre-productions samples should be arriving next week. Once approved (if no mistakes in pre-production models), then production will begin. I anticipate 1.25 months for actual running of production + 1 month for shipping. Estimated shipping to all looks like mid-Sept.
Just FYI - the time when I initiate production with the factory to pre-production time is typically taken up by a) queue for factory production time, b) lead time for acquisition of parts, c) development of paint mask + pad print tooling, d) any mold work prep. So figuring out the schedule is more of an art here than a precise science.
However, we are almost here!